27-07-2024, 09:19 PM
SJVN Ltd. has announced that it has received a Letter of Intent from the Government of Mizoram for the allotment of the Darzo Lui Pumped Storage Project. This marks SJVN's first venture in the state. The Darzo Lui Pumped Storage Project, with an installed capacity of 2,400 megawatts, is proposed to be developed across Darzo Nallah, a tributary of the Tuipui River. The estimated cost of completing the project is ₹13,947.50 crore. SJVN expects to complete the project in 72 months. An agreement formalising this venture is expected to be signed within the next three months between SJVN and the Government of Mizoram.